Buildings 4 & 5 Demolition & Soil Excavation – ABC Facility
Lockheed Martin believed that Buildings 4 & 5 at the former ABC site, and the soil there, impacted the groundwater in the vicinity of former sumps. Explore the work plans that detail the demolition of these buildings and the removal of the affected soil there.
Buildings 4&5 Demolition Plan
March 28, 2008
Air Monitoring Plan for Proposed Demolition Activities
March 17, 2008
Interim Remedial Measure Work Plan
March 5, 2008