Interim Remedial Action Plans
The following is a listing of the Interim Remedial Action Plans that Lockheed Martin developed to address existing environmental contamination at and around the former ABC facility.
Operations, Maintenance, and Monitoring Manual
August 26, 2011
Operations, Maintenance and Monitoring Manual
Revised August 26, 2010
Certificate of Occupancy Inspection Report
April 21, 2009
Certificate of Occupancy Inspection Report
April 21, 2009
Operation, Maintenance and Monitoring Manual
Revised January 29, 2009
Final Incident Corrective Action Report
January 29, 2009
IRAP Treatment Building Certificate of Occupancy
December 24, 2008
Revised CAP for Interim Groundwater Treatment System
October 28, 2008
Permit Application for CAP for Interim Groundwater Treatment System
September 30, 2008
Amendment to the CAP for Interim Groundwater Treatment System
September 30, 2008
Corrective Action Plan (CAP) for Interim Groundwater Treatment System
September 19, 2008
IRAP Construction Permits
July 24, 2006
IRAP – Revised & Completed
Revised February 27, 2006
IRAP
December 15, 2005
Draft IRAP
September 20, 2004